Executive Overview
ESD typically brakes custom marketing web site development into two phases: Static Web Site Phase and Dynamic Web Site Phase.
Static Web Site Phase
The Static Web Site Phase will take between four and six calendar weeks, and involve graphical theme creation, navigation and page style guide, and Site Map with complete web content and content presentation layout.
The graphical theme creation involves several design and review sessions of graphical proposals between the artists and the project stakeholder, with each review session allowing the artists to refine and mold the graphical proposals into the best-fit graphical theme.
Along with the graphical theme will be the development of the navigation style guidelines: Menu and sub menu layout, text and content styles, fonts and colors limitations, link styles, etc. Special attention will be given to ensure that the currently evolving client corporate web standards are observed and integrated.
The site map will help organize and allow the efficient navigation of the web site content, as well as ensuring all web content is linked and cross-linked for the most optimal and intuitive web site visitor access.
While mostly static content, the completed static web site will include some standard dynamic features such as news and trade show schedule sections, search facility, a careers section (if applicable), and the ability of a site visitor to sign up for a sales visit, white paper or product demo.
Sometimes we add features such as a database driven Distributors list that can be filtered by Province and Product/Service type, as well as the ability to have a web site user schedule a visit at an upcoming trade show or request a representative call.
The completed web site will be comprehensive with everything from complete BOBBY testing (for impaired access and disabilities act compliance) to the inclusion of standard verbiage such as legal disclaimer, privacy policy etc.
Dynamic Web Site Phase
The Dynamic Web Site Phase will involve the integration of presentation techniques and dynamic content. It will take anywhere from four weeks to several months depending on the level of dynamic content desired.
The adding of dynamic presentation techniques starts with adding Macromedia Flash snippets to provide a more graphically rich and interactive user experience and to supporting dynamic content enhancements for specific browser types and versions.
The dynamic content portion of this phase involves providing a series of user screens that allow company administrative (non-technical) users to maintain and update the marketing and customer facing information of the web site without requiring programming skills. Additional dynamic content often features links to legacy systems and other company data sources, such as the products databases.
Key Deliverables
- Graphical and content reface of the marketing web site, with improved content layout.
- Dynamic elements such as distributor locator, trade show scheduling, visitor registration for sales follow.
- Support for standard elements like Copyright Statements, Terms and Conditions, Policy Statement, Printer friendly pages, FAQs, News, etc.
- Support for all major versions of all major browser types.
- Support for impaired access standards.
Schedule and Deliverables
From completing many commercial marketing web sites, we have formed general rule of thumb estimates for the milestones, time, manpower and risks associated with a custom marketing web site. By applying those rule of thumb estimates, the following milestones can be determined:
Static Web Site Phase Milestones
|
Approx. Duration / Man Days
|
Comments / Risks
|
Graphical Theme Complete
|
1 Week / 1 Week
|
Depends on Stakeholder feedback and any applicable corporate guidelines.
|
Navigation Style Guidelines
|
1 Week / 2 Week
|
Depends on Stakeholder feedback and any applicable corporate guidelines.
|
Site Map and Content Finalization
|
2 Weeks / 2 Weeks (overlapped)
|
Depends on feedback and cooperation of Stakeholder organization. With less updating/restructuring/replacing of the current content this estimate will be reduced.
|
Phase one web site completion
|
3 Weeks / 5 Weeks
|
Development and Programming.
All static layout and standard dynamic sections like (News, visitor requests, trade show appearances, and distributor look up.)
|
Note: Five to Six Calendar Weeks, Ten Manpower Weeks.
Dynamic Web Site Phase Milestones
|
Approx. Duration
|
Comments / Risks
|
Dynamic Flash Content
|
4 Weeks / 5 Weeks
|
Will depend on Stakeholder feedback.
|
Dynamic Content Support
|
To Be Determined
|
Will depend on Stakeholder feedback.
|
Internationalization (multiple language Support)
|
N/A
|
Is this a possible requirement?
|
Legacy System Integration
|
N/A
|
If any they need to be identified.
|
Note: Time frame to be determined with more analysis and assessment of the requirements. |